Earned Value Analysis (EVA) or Earned Value Management
(EVM) is a systematic PM methodology that allows the project manager to measure
the amount of work actually performed on a project with respect to planned cost
and schedule. It has the ability to combine measurements of the project triangle:
scope, time, and costs.
In NASA Library, the first version of Earned
Value Management (EVM) was developed by its Defence Department (DoD) to track programs
during the 1960 and since 2005, EVM has been a part of general federal project
risk management. Now, it is used in the private sector such as consulting firms,
IT, automotive, manufacturing, aerospace, and educational establishments
worldwide.
It has no relationship to the investment value
or benefit of the project for which it has been funded. However, earned value
matrix can be used to measure the cost and schedule inputs to Devaux's Index
of Project Performance (DIPP), which integrates schedule and cost performance
with the planned investment value of the project across the project management
triangle.
Earned value calculations require the following
input data to measure the performance of the project:
TERM
|
ABBREVIATION
|
MATHEMATICAL INTERPRETATION
|
DEFINITION
|
PLANNED VALUE
|
PV
|
Also
called as Budgeted Cost for Work Scheduled (BCWS)
|
Authorized
Budget assigned to the scheduled work
|
EARNED
VALUE
|
EV
|
Also
called as Budgeted Cost for Work Performed (BCWP)
|
Measure of
actual work performed expressed as budget authorized for that work
|
ACTUAL
COST
|
AC
|
Also
called as Actual Cost of Work Performed (ACWP)
|
Actual
cost incurred for the work performed
|
With this Input, you can derive the following calculations:
Project Variances:
TERM
|
ABBREVIATION
|
MATHEMATICAL
INTERPRETATION
|
DEFINITION
|
SCHEDULE VARIANCE
|
SV
|
= EV - PV
|
Amount by which project is ahead or behind plan
|
COST VARIANCE
|
CV
|
= EV - AC
|
Amount by which actual cost is ahead or behind planned cost
|
VARIANCE AT COMPLETION
|
VAC
|
= BAC - EAC
|
Estimated difference in cost at the completion of the
project compared to Plan
|
Performance
Indices:
SCHEDULE PERFORMANCE INDEX
|
SPI
|
= EV/PV
|
Measure of Schedule efficiency expressed as Earned Value to
Planned Value
|
COST PERFORMANCE INDEX
|
CPI
|
= EV/AC
|
Measure of Cost efficiency expressed as Earned Value to
Actual Cost
|
Note: CPI < 1 Project over budget , CPI > 1 project under budget, and CPI = 1 means project is on estimated budget.
SPI < 1 Project behind schedule, SPI > 1 Project ahead of schedule, and SPI = 1 means project is on schedule.
Project
Forecasting:
ESTIMATE AT COMPLETION
|
EAC
|
Option 1) = AC +
(BAC - EV)
Option 2) = BAC/CPI Option 3) = AC + [(BAC- EV)/(CPI * SPI)] |
Expected
Total Cost of project = sum of Actual Cost till date and Estimate To Complete
remaining work
Option 1; Remaining Work will be done at the planned/budgeted rate Option 2; Remaining Work will be done at the present CPI Option 3; Remaining Work will be done considering present SPI and CPI |
ESTIMATE TO COMPLETE
|
ETC
|
= EAC - AC
|
Expected Cost to finish the remaining project work
|
TO-COMPLETE PERFORMANCE INDEX
|
TCPI
|
Option 1) = (BAC- EV)/(BAC- AC)
Option 2) = (BAC- EV)/(EAC- AC) |
Measure of
the cost performance required with the remaining resources to meet goal.
Work Remaining/Funds Remaining Option 1; Efficiency that must be maintained to complete on Planned Budget Option 2; Efficiency that must be maintained to complete on current EAC |
ESTIMATED COMPLETION DATE
|
ECD
|
= Project Start Date + (Planned Duration/SPI)
|
Expected Completion Date of the project
|
Note: TCPI define as how to effectively should use resources to complete the project on budget. TCPI < 1 is good for project.
EVM/EVA contributes to; Improve communication and
visibility with stakeholders, Reduce risk, Profitability analysis, Project
forecasting, Better accountability and Performance tracking.
You can comment us about
this article and EVM template that help you to understand Earned Value Analysis (EVA) or Earned Value Management (EVM) and compute the performance of the project. Moreover, help us to write
more about engineering technologies and methodologies.
0 comments: